|
Previous summer and fall: Homeowners work with Studio Z and the contractor to take the project from an initial concept to a fully elaborated design. Studio Z completes the final "construction documents" (blueprints and specifications) in the fall, and the plans are submitted to the city authorities for approval. Demolition of the existing deck and old garage takes place in December. Scheduling begins for the masonry subcontractor, who will dig and pour foundation footings.
February 5: The masons begin excavating for the foundation footings. They immediately discover a problem: an old cistern, used to collect rainwater long ago, is located precisely where the foundation for the new addition meets the house. See Expect the Unexpected (at left) for more details. Digging trenches for the garage footings proves uneventful.

February 13: Footings for the garage/office foundation are poured, using two full trucks worth of concrete.
February 17: The concrete block foundation for the garage office has been finished.

February 20: The old cistern has been emptied out, inspected, and filled up to the level of the footings with pea gravel. The footings for the addition are then poured.
March 5: The concrete block foundation for the mudroom addition has been laid down, and the old concrete back door steps have been removed.
March 8: With the foundation walls done, the carpenters can begin work. The floor deck of the addition has been framed, and the walls are going up.
March 14: The walls are up and sheathed with plywood, and the roof of the addition is being framed.
March 20: The addition roof has been framed, and the interior partition wall, with pocket door hardware, has also been framed.
March 27: Casement windows have been set in the rough openings on the addition, and the crew has begun to shingle the roof. The small roof over the back door, and the brackets which support it, has also been framed and joined to the main roof.

March 30: The roof shingling has been finished, and the new back door has been hung in its opening. Since the addition is now weather-tight, interior work can begin.

April 3: Work resumes on the garage/office, anticipating the arrival of the structural insulated panels. The old concrete slab is removed (with some difficulty), and 4 inches of sand is compacted to form the base for the new slab; the sand is covered with a vapor barrier and wire mesh.
April 6: Plumbing and heating pipes for the addition have been roughed in and are awaiting plumbing and mechanical inspections.
April 10: The slab for the new garage was poured after the prepared base was inspected by the city authorities.

April 12: The first batch of SIPs (structural insulated panels), including the downstairs and upstairs walls, arrive on site and are unloaded.
April 13: Siding has started to go up on the addition; rather than wood or vinyl, SZA and the contractor suggested a cementitious product which is less expensive and should be more durable.

April 17: With some extra help, the crew raised the wall panels for the first floor of the garage/office, each of which were fabricated in one piece. This process would normally be accomplished with a crane, but the site is not large enough.
April 18: The office roof trusses were delivered (at 7am) and left in the front yard until they could be carried back to the site - by hand.

April 23-26: The second story floor and wall panels are erected.
|